Video Report on Construction for January 2024:

  • Completing the brickwork for the first floors of 8 cottages
  • Completed concrete pouring for all 12 foundations across all cottages in the first phase
  • Poured interfloor slabs for the 1st and 2nd cottages
  • Installing formwork for the monolithic slab of the 3rd and 4th cottages

Popular news

Construction Progress of AcademHoff – September 2023
25.09.2023
AcademHoff
Construction
Construction Progress of AcademHoff - September 2023
Read in full
Construction Progress of AcademHoff – October 2023
20.10.2023
AcademHoff
Construction
Construction Progress of AcademHoff – October 2023
Read in full
Construction Progress of AcademHoff – November 2023
22.11.2023
AcademHoff
Construction
Construction Progress of AcademHoff – November 2023
Read in full
Construction progress of Concept Riviera – February 2024
28.02.2024
Concept Riviera
Construction
Construction progress of Concept Riviera – February 2024
Read in full
Construction Progress of AcademHoff – December 2023
20.12.2023
AcademHoff
Construction
Construction Progress of AcademHoff – December 2023
Read in full
call-icon