Video report of construction for November 2023:

  • Common area screed completed 100%.
  • Roofing finished 100%.
  • Storm drainage system installed.
  • Partitions for commercial spaces on the first floor constructed.
  • Demolition of scaffolding completed.

Popular news

Construction Progress of AcademHoff – September 2023
25.09.2023
AcademHoff
Construction
Construction Progress of AcademHoff - September 2023
Read in full
Construction Progress of AcademHoff – October 2023
20.10.2023
AcademHoff
Construction
Construction Progress of AcademHoff – October 2023
Read in full
Construction Progress of AcademHoff – November 2023
22.11.2023
AcademHoff
Construction
Construction Progress of AcademHoff – November 2023
Read in full
Construction progress of Concept Riviera – February 2024
28.02.2024
Concept Riviera
Construction
Construction progress of Concept Riviera – February 2024
Read in full
Construction Progress of AcademHoff – December 2023
20.12.2023
AcademHoff
Construction
Construction Progress of AcademHoff – December 2023
Read in full
call-icon