Riviera construction progress – April 2024
1 stage of construction:
Cottages on the first floor:
- Finished waterproofing of foundations
- The floor of the 2nd floor was poured with concrete
- We are laying bricks on the 3rd floor
Cottages inside Chamomile
- Waterproofing of the foundations is completed
- Formwork has been installed and we are reinforcing the floor between the 1st and 2nd floor
Individual residences:
- Bricklaying of the 1st floor was completed
- We continue the preparatory work for speed construction: 2, 3 and 4 phases