Video report on construction for March 2024:

  • Fenced and cleared the entire area
  • Delivered 760 loads = 14,500 cubic meters of soil: clay, black soil, sand
  • Leveled and compacted the soil

Phase 1 of construction:

Cottages on the front line:

  • Laying bricks for the 2nd floor
  • Installing formwork for pouring the floor slab between the second and third floors

+Cottages in the middle “Daisy”:

  • Laying bricks for the 1st floor
  • Preparing for the construction of the 2nd, 3rd, and 4th phases

Popular news

Construction Progress of AcademHoff – September 2023
25.09.2023
AcademHoff
Construction
Construction Progress of AcademHoff - September 2023
Read in full
Construction Progress of AcademHoff – October 2023
20.10.2023
AcademHoff
Construction
Construction Progress of AcademHoff – October 2023
Read in full
Construction Progress of AcademHoff – November 2023
22.11.2023
AcademHoff
Construction
Construction Progress of AcademHoff – November 2023
Read in full
Construction Progress of AcademHoff – December 2023
20.12.2023
AcademHoff
Construction
Construction Progress of AcademHoff – December 2023
Read in full
Construction progress of Concept Riviera – October 2023
23.10.2023
Concept Riviera
Construction
Construction progress of Concept Riviera - October 2023
Read in full
call-icon