Works completed in November 2023:

  • Poured the foundation base for 8 cottages along the first shoreline.
  • Poured foundation walls for 2 cottages.
  • For 2 residences and 4 cottages along the second shoreline: performed earthworks and poured the foundation bases.

Popular news

Construction Progress of AcademHoff – September 2023
25.09.2023
AcademHoff
Construction
Construction Progress of AcademHoff - September 2023
Read in full
Construction Progress of AcademHoff – October 2023
20.10.2023
AcademHoff
Construction
Construction Progress of AcademHoff – October 2023
Read in full
Construction Progress of AcademHoff – November 2023
22.11.2023
AcademHoff
Construction
Construction Progress of AcademHoff – November 2023
Read in full
Construction progress of Concept Riviera – February 2024
28.02.2024
Concept Riviera
Construction
Construction progress of Concept Riviera – February 2024
Read in full
Construction Progress of AcademHoff – December 2023
20.12.2023
AcademHoff
Construction
Construction Progress of AcademHoff – December 2023
Read in full
call-icon